Dorna Automation Solutions (DAS)
Call +1 (480) 744-6106

Palletizer Installation: What to Expect From Delivery to First Pallet

Most of the risk in a palletizer project is not the robot — it is the week it arrives. Who receives it, where it stands, whether power and air are ready, and who learns to run it decide whether you are stacking pallets quickly or losing days to small surprises. Here is the installation process for a cobot palletizer cell, step by step, and what your plant should have ready at each stage.

Step 1: Confirm the sizing before anything ships

Installation starts long before a truck arrives, with the five sizing numbers: master case length × width × height, heaviest case weight, sustained cases per minute, cases per pallet, and pallet size. Those numbers set the gripper, the pallet pattern and the cell layout. If you have not measured them yet, start with our sizing guide, Pallet Patterns and Case Sizing — and size to your heaviest case, not your average. Our rental cells handle cases up to 20 kg (44 lb), with a robot reach of up to 1,880 mm.

This is also when the layout is settled. A single fixed cobot picks from the conveyor and places to pallet positions on its left and right. It cannot directly serve four pallet positions — that takes a linear rail or a second robot, and it is far cheaper to learn that on paper than on installation day.

Step 2: Get the site ready

A cobot cell is deliberately simple to host, but simple is not the same as unprepared. Before delivery, confirm each item on this checklist:

Site itemWhat to have ready
Floor spaceA typical cell is about 3,000 × 3,000 mm, with two pallet stations of 1,100 × 1,100 mm and the conveyor infeed at the top centre
Power110 V, maximum 15 A, available at the cell
Compressed airAn air connection at the cell for the gripper
ReceivingA coordinated delivery time, a clear route in, and a pallet jack or forklift to move the equipment on site
Sample casesFilled, sealed cases of every format you will run, so patterns can be taught on real boxes
PeopleThe operators who will run the cell, available for training during start-up

Walk the delivery route once, too: door widths, turns and floor condition between the dock and the line end. And settle the safety picture in advance, not during the install — our guide Are Cobot Palletizers Safe? covers the risk-assessment checklist. Safety guides and a cage are options fitted when your assessment or plant rules call for them, and the typical layout includes a safety light curtain on the open side.

Step 3: Delivery — typically 3 to 4 weeks

Delivery to your site typically takes 3–4 weeks. The robot ships on a wooden pallet, so receiving it is a planned event, not a surprise: agree the delivery time in advance, have the pallet jack ready, and have the cell area cleared before the truck arrives. A short photo of your line end — conveyor position, available floor area and where full pallets will leave — helps confirm the layout one last time before the equipment is positioned.

Step 4: Installation and start-up on site

With the site ready, installation is positioning and connecting the cell, not construction. The robot is set so its front faces the conveyor infeed, the two pallet stations are placed within its reach on the left and right, and the cell is connected to that 110 V supply and compressed-air line. Then comes start-up: checking pick and place motion with your real cases, confirming the grip on your heaviest case, and running the cell at your sustained rate — the rate it must hold all shift, which is a different test from a short peak. For how that rate is calculated, see How Many Cases Per Minute Can a Cobot Palletizer Handle?

We attend on site for installation and start-up. That matters because the small adjustments — conveyor handoff, case presentation, placement accuracy on the first layers — are made fastest with the person who designed the cell standing at your line, watching your actual cases run.

Step 5: Recipes and training

A palletizer is only useful if your team can run it without calling anyone. During the same visit we create the recipes for your pallet patterns — the pick, layer pattern and placement for each case format you run — and train your operators on start, stop, pallet changeover and switching between recipes. If you run a 12-pack and a 24-pack, each gets its own stored recipe, taught on sample cases you supplied.

Keep the people who trained in the loop for the first full shifts. Most early questions are not faults; they are pattern, case or pallet-supply details that a trained operator resolves in minutes once they have seen them once.

What can delay an installation

Why rental changes the installation risk

A purchased palletizer makes installation a point of no return: the capital is spent before the first pallet is stacked. A palletizer rental reverses that order. Our rental is $1,999/month with zero upfront, and installation and maintenance are included — so the cell is installed, started up and proven on your real line, with your real cases, as part of the rental, not as a separate integration gamble. The comparison behind that choice is broken down in Palletizer Rent vs Buy and How Much Does a Robotic Palletizer Cost?

The bottom line

A smooth palletizer installation is mostly preparation: confirm the five sizing numbers, clear about 3,000 × 3,000 mm, have 110 V power and compressed air at the cell, plan receiving with a pallet jack, and have sample cases and operators ready. Delivery typically takes 3–4 weeks, and installation, start-up, training and recipe creation happen on site. Do those few things, and installation day is what it should be — the day your line stops stacking by hand.

Planning an installation? Start with a free line walkthrough

Send us your case size, heaviest case and cases per minute, and a photo of your line end. We will confirm the layout, footprint and utilities for your plant: $1,999/month, zero upfront, installation and maintenance included.

See Palletizer Rental

or call +1 (480) 744-6106

Explore palletizer rental